Mark writes: Ferry Lass has been turned over and the brass strip on the keel removed. The keel is still drying and here’s the plan:
Tuesday, 10 March, 1000: Meet at the shed. Sand the sides and bottom of the keel, being careful not to take too much off the edges. Prime keel, first of two coats. Needs two or three people.
Wednesday, 11 March, 1000: Meet at the shed. Sand keel’s first coat primer very lightly and apply a second coat.
Volunteers please let me know at mameredith(at)btinternet.com
The new brass keel strips should arrive on Wednesday or Thursday and we can then plan the next phase of work.